Sidewalk or Curb - Repair at 4514 8 Av SW

CLOSED No Action Required - Close SR. Permit: Sidewalk is on list for replacement in 2019, Sidewalk was inspected and temporary asphalt repair has been made until concrete can be replaced. Concrete season run June to Nov; our schedule changes too often due to weather we cannot give fixed date. Please Note; Due to high volume of permits; replacement maybe delayed until 2020 season. Sidewalk is not a hazard. Sorry for any inconvenience. - about 5 years ago #19-00238690
Report
Submitted Mon Mar 25, 2019

Temporary asphalt sidewalk sections are uneven and are a tripping hazard. Needs to be replaced with concrete to match the existing cement sidewalk.

Nature of Concern: Heaving / Sinking Sidewalk

Type of Sidewalk: Asphalt

Specific Details: Temporary asphalt sections from construction are uneven and pose tripping concern. Need to be replaced with cement to match existing side walk.

Specific Location: 4512 / 4514 8 Ave SW



address: 4514 8 AV SW

coordinates x,y: -10658.611204593499, 5656557.908294507

coordinates lat,lng: 51.04518616666667, -114.152

ward: 8

Timestamp Description
Tue Mar 26, 2019 09:44am Closed with status: No Action Required - Close SR. Permit: Sidewalk is on list for replacement in 2019, Sidewalk was inspected and temporary asphalt repair has been made until concrete can be replaced. Concrete season run June to Nov; our schedule changes too often due to weather we cannot give fixed date. Please Note; Due to high volume of permits; replacement maybe delayed until 2020 season. Sidewalk is not a hazard. Sorry for any inconvenience.
Tue Mar 26, 2019 09:44am Field Inspection >> No Action Required - Close SR
Mon Mar 25, 2019 06:06pm Opened
Mon Mar 25, 2019 06:03pm Submitted via iPhone Iphone